Half of the automated measures marked as implemented hadn’t been.
A preliminary analysis of measures resolved by July 2021 showed that 50% of automated measures were being incorrectly marked as implemented.
Status changes didn’t capture the reasoning behind them, and there was no way to verify the impact of the work from inside the workflow. The savings we reported were only as good as a status dropdown.
50%
of automated measures resolved by July 2021 were incorrectly marked as implemented
Reduce the number of measures resolved with the wrong status.
Make what was done on a measure visible before it is closed.
Prove what the work achieved at the moment the measure is closed.
Interviews with customers and internal stakeholders showed that people wanted specific changes to the Measures workflow. Annotations, conversations with teammates, and measurement and verification (M&V) all happened outside the product, so stakeholders drifted out of step.
Mixpanel told the same story. About 45% of the time, users left a comment after closing a measure. They had more to say than the status allowed. But comments were free-form, so our advisory team sorted them by hand to work out what had actually been implemented.
~45%
of closed measures got a comment after closing, which the advisory team sorted by hand
Measure creation
“My feedback doesn’t influence future measures”
Measure notification
“I’m not always aware of which measures remain open and need work”
Investigate and prioritize
“It’s hard to tell whether a measure is actionable from the information given”
Working on a measure
“It’s hard to talk with others about a measure and where it is in the workflow”
Closing a measureOur focus
“My work isn’t accurately reflected when I close a measure”
M&V and reporting
“The impact of my work isn’t represented or verified”
Measure feedback
“I don’t have an easy way to update measure assumptions”
Tom, building engineer. Works assigned tasks in the field and reports progress to the chief engineer.
01Reviews assigned tasks and the preventive maintenance schedule in the work order system
OpportunityDeeper integration with work order systems
02Investigates the task in the field or through the building automation system
OpportunityMobile tools to review a measure, validate the observed issue, and share progress
03Resolves the task and completes maintenance, tracking time and steps taken
OpportunityMobile tools to work in the field with up-to-date information and track status
04Reports progress and work to the chief engineer
OpportunityOne place to track actions taken, like notes, so they tie back to impact
The brief
Give the people doing the work a transparent, structured way to show it, so every closed measure reflects what really happened and what it saved.

Closing a measure now asks for a status, a resolution (implemented or not implemented), and a reason. Each option comes with a description, so “closed” no longer has to mean “done”.
Tradeoff More clicks at the moment someone wants to be finished. We kept the fields short and the defaults sensible so the extra step felt like a confirmation, not a form.
Every measure keeps an activity log of status changes, comments, and uploads, with who did each one and when.
Tradeoff A busy measure has a long log. It leads with the latest events and puts the full history behind “View all”.
Teams can attach supporting documents, such as an M&V report, straight to the measure. The proof lives next to the claim instead of in someone’s inbox.
Tradeoff Attachments are only as good as what people upload. They support verification, but they don’t replace it.
Each measure leads with its avoidable impact: cost, emissions, electricity, and gas. Beside the observed issue, a chart compares usage before and after implementation.
Tradeoff A chart can’t verify every measure on its own. Weather, occupancy, and data gaps all muddy the comparison, so it informs the resolution rather than deciding it.
Everything needed to close a measure honestly, on one screen.

The portfolio view: what is open, who owns it, and what it is worth.

For the engineer in the field, where the work actually happens.

Before
50%
of automated measures marked implemented in error
Six months after release
73%
fewer improperly resolved measures in the first six months after release